Commercial Road Tops Out

Commercial Road Tops Out
Commercial Road Tops Out

2nd December 2020

The full DfMA frame has topped out at Commercial Road working with our client PCE. The entire build phase for the 14 storey hybrid precast frame was a mere 17 weeks. The site team were able to hit a 5 day floor cycle time with only 8 operatives below the hook. 

By making use of our full range of digital build technologies we were able to ensure there were virtually no issues to be resolved on site when bringing the large format concrete elements together.